High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.
Satellite view of this address

Where it is · E/825, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Santacruz / KharUltra-luxury

Bandra's quieter northern neighbour — low-rise lanes going boutique.

Growth drivers:
Society redevelopment, airport and BKC equidistance.
Who buys here:
Professionals wanting Bandra adjacency with less noise.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
G.S. DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800003297
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.