High risk
  • Possession date passed. The proposed possession date (Oct 2018) has passed with construction at 67.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2018 per the RERA filing.
Satellite view of this address

Where it is · CTS NO597/A 597/B, Kurla

Promoter

Builder profile

Builder
RAJAN CHANDRAKANT TIPNIS HUF

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800003279
Status
Ongoing
Stage
Certificate Signed
Possession
October 2018
Construction
67.5% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.