Sept 2018
Possession
47.3%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 47.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2018 per the RERA filing.
Satellite view of this address
Where it is · PLOT NO 253 SECTOR 17 ULWE, Panvel
Promoter
Builder profile
SUNRAYS CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000010678
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2018
- Construction
- 47.3% complete
- Units sold
- 0 of 0
Similar projects in Panvel
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
SHREE SAI CORNER
PanvelPoss. March 2027
SAI WORLD CITY PHASE II
PanvelPoss. April 2026
Godrej Golf Side Estate II
PanvelPoss. December 2028
AAKAR 88
PanvelPoss. December 2030
ANANT COMMERZ
PanvelPoss. December 2030
KONNARK ASTRA
PanvelPoss. December 20331 complaint
Adinath Crystal
PanvelPoss. December 2028
Shree Sahayya Prime
PanvelPoss. December 2028
Keep exploring
Where this project sits, who built it, and how Panvel compares.
In Panvel
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.