Delayed projects in Raigarh
1,018 MahaRERA-registered projects in Raigarh are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 2 of 6
- Blue Crest7.6 yr overdueElinor Infra LLP · Karanjade, RaigarhP52000009702· 80.3% built· 1 complaint
- 5P ARIA7.6 yr overdue5P Developers · Neral, RaigarhP52000013706· 73.3% built· 1 complaint
- GURU AANGAN7.6 yr overdueFSK BUILDERS & DEVELOPERS PRIVATE LIMITED · Ulawe, RaigarhP52000010422· 35.5% built
- SAI NIWAS7.6 yr overdueMEDAPARAMPIL GANGADHARAN SADASHIVAN · Bamandongri, RaigarhP52000011554· 9.1% built· 1 complaint
- SIDDHIVINAYAK HERITAGE7.6 yr overdueSIDDHIVINAYAK DEVELOPERS · Panvel, RaigarhP52000002557· 90.9% built
- SILVER CREST7.6 yr overdueGEOMATRIX DEVELOPERS LLP · Panvel, RaigarhP52000008393· 79.2% built
- Anand Nagar Phase 27.6 yr overdueAnubhavshri Realty Pvt. Ltd. · Lonere, RaigarhP52000003466· 57.3% built
- Vrindavan Arcade7.6 yr overdueSHREEJI ENTERPRISES · Bopele, RaigarhP52000013103· 90.9% built
- VISHWAVARAD RESIDENCY7.6 yr overdueVARSHA NARESH LALWANI · Karanjade, RaigarhP52000012442· 65% built
- SAPTASHRUNGI APARTMENT7.6 yr overduePRADEEP RATAN PATIL · Chikhale, RaigarhP52000012255· 88.6% built
- Anusaya Heights7.6 yr overdueJaimakk Infra · Karanjade, RaigarhP52000000651· 90.9% built
- IMPERIAL HEIGHTS7.6 yr overdueSHYAM BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000009768· 67.3% built
- TULJA ELITE7.6 yr overdueM/S IMAGINE CONSTRO ARTS PRIVATE LIMITED · NERAL, RaigarhP52000015338· 90.9% built
- GOURI SHARDA7.6 yr overdueSHANKAR SADU MHATRE · Panvel, RaigarhP52000007381· 32.7% built
- SAI SAGAR7.6 yr overdueSAI INFRA · Ulawe, RaigarhP52000006739· 68.2% built
- SHREE GANESH APARTMENT7.6 yr overdueSAFFRON DEVELOPERS · Ulawe, RaigarhP52000006424· 36.4% built
- SATYAM APARTMENT7.6 yr overdueSHANTI DEVELOPERS · Taloje Panchnad, RaigarhP52000012326· 45% built
- SAI SPARSH7.6 yr overdueDG Enterprises · Ulawe, RaigarhP52000007969· 90.9% built
- MALHAR RESIDENCY7.6 yr overduePRASHANT S THORAT · Panvel, RaigarhP52000008729· 95.5% built
- BHOSALE MARIGOLD7.6 yr overdueLEENA ARJUN GARAD · Ulawe, RaigarhP52000012668· 90.9% built
- RIVERA ESTATES7.6 yr overdueOmega Constructions · Khalapur, RaigarhP52000010090· 41.8% built· 1 complaint
- SUKHKARTA 27.6 yr overdueIMAGE BUILDERS · Khopoli, RaigarhP52000010927· 75.5% built
- KRISHNA PALACE7.6 yr overdueKRISHNA ENTERPRISES · Ulawe, RaigarhP52000009559· 61.7% built
- BALAJI RESIDENCY COMPLEX7.6 yr overdueDev Builders and Developers · Hedutane, RaigarhP52000003419· 90.6% built
- SHREE SAMARTH DARSHAN7.6 yr overdueSHREE SAMARTH RESIDENCY · Dhamote, RaigarhP52000001859· 90.9% built
- Payal Palace7.6 yr overdueNanji Murji Dama · near ramseth thakur stadium, RaigarhP52000009512· 90.9% built
- ESSENTIA7.6 yr overdueShagun Realty · Ulawe, RaigarhP52000001961· 55% built
- RICOVERA7.6 yr overdueSUNANDA MAHADEV KOLI · Panvel, RaigarhP52000011899· 90.9% built
- Sanwariya Darshan7.6 yr overdueshyam sunder satyanarayan dad · Kharkopar, RaigarhP52000006340· 90.9% built
- DARSHAN7.6 yr overdueVIRENDRA VERMA · Uran, RaigarhP52000012198· 65.9% built
- SHIVALAY RESIDENCY7.6 yr overdueRAJU GHANSHYAM PURSWANI · Varasoli, RaigarhP52000006833· 46.4% built
- DIVYA HEIGHTS7.6 yr overdueSAI HOMES DEVELOPERS · Karanjade, RaigarhP52000013582· filed Dec 2017 → now Dec 2018· 90.9% built· 2 complaints
- Zion7.6 yr overdueSai Mahaavir Developers · Panvel, RaigarhP52000001426· 90.9% built
- Vrindavan Garden - Tulip7.6 yr overdueSairaj Enterprises · Karjat, RaigarhP52000004716· 90.9% built
- SIDDHIVINAYAK GARIMA7.6 yr overdueSIDDHIVINAYAK HOMES · Panvel, RaigarhP52000001125· 89.1% built
- SIMRAN COMPLEX7.6 yr overdueF & R DEVELOPERS · MAHAD, RaigarhP52000012954· 66.4% built· 1 complaint
- PANCHRATNA PARK7.6 yr overdueHINDUSTAN CONSTRUCTION BUILDERS & DEVELOPERS · Panvel, RaigarhP52000008794· 81.3% built
- SHAMA VILLA7.6 yr overdueROYAL ENTERPRISES · Panvel, RaigarhP52000006785· 39.1% built
- YASH COMPLEX7.6 yr overdueYASH DEVELOPERS · Pen (M Cl), RaigarhP52000010152· 62.7% built
- WHITE WOODS7.6 yr overdueShagun Realty · ULWE, RaigarhP52000001185· 90.9% built
- VINAYAK SAI RESIDENCY47.6 yr overdueSAI BUILT CON · Pen (M Cl), RaigarhP52000001360· 80% built
- TARIQUE SAPPHIRE7.6 yr overdueKOHINOOR DEVELOOPERS AND REALTORS · Panvel, RaigarhP52000010945· 61.8% built
- Mauli Residency7.6 yr overdueMauli Enterprises · Panvel, RaigarhP52000007675· 90.9% built
- SAUBHAGYA DARSHAN7.6 yr overdueSAUBHAGYA BUILDERS · Karanjade, RaigarhP52000003233· 63.6% built
- MY SKY RESIDENCY PHASE I7.6 yr overdueASHAPURA ABODE · Dhamote, RaigarhP52000001455· 61.4% built
- SANA RESIDENCY7.6 yr overdueMOHD FAIZAL MOHD YASIN MANSURI · DRONAGIRI, URAN, RaigarhP52000014640· 83.6% built
- REDWOOD ICON7.6 yr overdueREDWOOD BUILDCON · Pen (M Cl), RaigarhP52000009374· 54.5% built
- WHITE CARNATION7.6 yr overdueSPS CONSTRUCTION · ULWE, RaigarhP52000001088· 90.9% built
- PRAGATI NIVAS7.6 yr overduePRAGATI DEVELOPERS · Ulawe, RaigarhP52000007296· 74.9% built
- KRISHNA HARMONY7.6 yr overdueRADHE KRISHNA BUILDERS · Karanjade, RaigarhP52000003078· 81.8% built
- SIMRAN MAJESTIC7.6 yr overdueVIKRANT VIKAS RAIKAR · Panvel, RaigarhP52000002117· filed Jun 2018 → now Dec 2018· 82% built
- GURUKUL RESIDENCY7.6 yr overdueSHREE BRAMHA ENTERPRISES · Mamdapur, RaigarhP52000011499· 21.8% built
- NANDVIHAR7.6 yr overdueBhagwati Developers · Khalapur, RaigarhP52000009560· 74.5% built
- Green Acre- Phase II7.6 yr overdueDharti Developers · Vakadi, RaigarhP52000000697· 67.3% built
- ARADHYA RESIDENCY7.6 yr overdueMEERA DEVELOPERS · KARANJADE, RaigarhP52000006254· 81.8% built
- PINNACLE DREAMZ7.6 yr overdueM/S. PINNACLE CONSTRUCTION COMPANY · Panvel, RaigarhP52000006971· 81.4% built
- STAR HOMES7.6 yr overdueSTAR HEIGHT BUILDERS LLP · Bokadvira, RaigarhP52000013196· 66.4% built· 2 complaints
- SUKHKARTA 17.6 yr overdueIMAGE BUILDERS · Khopoli, RaigarhP52000010590· 47.7% built
- Malav Vallencia7.6 yr overdueMALAV PROMOTERS & DEVELOPERS · Khalapur, RaigarhP52000000076· filed Jun 2018 → now Dec 2018· 72.7% built
- MUNOTH EMPRESS7.6 yr overdueARHAM DEVELOPERS · Panvel, RaigarhP52000002872· 79.1% built
- INSIGNIA7.6 yr overdueShagun Realty · Ulawe, RaigarhP52000005695· 48.6% built
- APEX STEP7.6 yr overdueAPEX REALTORS · Karanjade, RaigarhP52000007778· 90.9% built
- RUSHIKESH7.6 yr overdueRUSHI DEVELOPERS · Karanjade, RaigarhP52000005675· 45.9% built
- Malati Heritage7.6 yr overdueMalati Enterprises · Khalapur, RaigarhP52000004604· 90.9% built
- NEELKANTH RESIDENCY7.6 yr overdueNEELKANTH ENTERPRISES · Panvel, RaigarhP52000009397· 90.9% built
- AMAR JYOT7.6 yr overdueAMARDEEP DEVELOPERS · Mamdapur, RaigarhP52000010025· 59.2% built
- Shelter Avenue7.6 yr overdueAbu Zaid Khan · ULWE, RaigarhP52000008295· 54.1% built
- PRAYAG YASH PHASE I7.5 yr overduePRAYAG PROPERTIES · ADAI NR GAON DEVI MANDIR, RaigarhP52000011038· filed Dec 2018 → now Feb 2019· 90.9% built
- Indiabulls Savroli - 17.5 yr overdueSylvanus Properties Limited · Khalapur, RaigarhP52000001481· 78.2% built· 16 complaints
- SIDDHIVINAYAK RESIDENCY7.5 yr overdueSUNIL RAGHUNATH VIDHATE · Pen (M Cl), RaigarhP52000013005· filed May 2018 → now Feb 2019· 62.3% built
- Cluster F7.4 yr overdueShibam Associates · Neral, RaigarhP52000008779· 90.9% built
- SUNSHINE PHASE II7.4 yr overdueMUBIN MOHAMMED IQBAL JUMANI · Dahiwali T. Waredi, RaigarhP52000012800· 49.1% built
- ORCHID7.4 yr overdueSHRI HARI DINESHCHANDRA CORPORATION · Panvel, RaigarhP51700006223· 49% built
- UMA PRIDE7.4 yr overdueSHREE RAJ LAND DEVELOPERS · Ulawe, RaigarhP52000006360· 90.9% built
- APEX VILLA7.4 yr overdueAPEX BUILDERS & DEVELOPERS · Karanjade, RaigarhP52000006690· 90.9% built
- SAI SAAKSHAAT - WING E7.4 yr overdueSAI SHIRDI CONSTRUCTIONS · Panvel, RaigarhP52000000509· 90% built
- SHREEJI AMREET7.4 yr overdueSHREEJI LIFESPACES BUILDERS & DEVELOPERS · Ulawe, RaigarhP52000009597· 31.2% built
- METRO APARTMENT7.4 yr overdueMETRO ENTERPRISES · Panvel, RaigarhP52000003818· 18.2% built
- ELITE GRANDEUR7.4 yr overdueNATHDWARA LIFESPACE PVT LTD · Panvel, RaigarhP52000012375· filed Mar 2018 → now Mar 2019· 96.8% built· 1 complaint
- SKY CORRAL7.4 yr overdueSKY CITY DEVELOPERS · Uran, RaigarhP52000003181· 90.9% built
- BHAGIRATH RESIDENCY7.4 yr overdueBHAGIRATH CORPORATION · Panvel, RaigarhP52000004859· 45.4% built
- MEGA NEXUS7.4 yr overdueMohammed Yusuf Salim Chaudhary · Ulawe, RaigarhP52000006659· 90.9% built
- RAMJI RESIDENCY7.4 yr overdueVITTHAL RAMJI MORE · Khalapur, RaigarhP52000006271· 68.5% built
- RATAN VILLA7.4 yr overdueTULSI CONSTRUCTIONS COMPANY · PANVEL, RaigarhP52000009763· 64.1% built
- KHUSHBOO AVENUE7.4 yr overdueKHUSHBOO DEVELOPERS · Panvel, RaigarhP52000006389· 90.9% built
- KRISHNA DHAM7.4 yr overdueLANDMARK CONSTRUCTION · Panvel, RaigarhP52000009937· filed Mar 2018 → now Mar 2019· 58.5% built
- YASHRAJ CORNER7.4 yr overdueYASHRAJ ENTERPRISES · NAVI MUMBAI, RaigarhP52000007567· 90.9% built
- S.N.PLAZA7.4 yr overdueSHAHNAWAZ SULTAN SHAIKH · Mamdapur, RaigarhP52000013851· 72.7% built
- Deccan Residency7.4 yr overduePRAVEEN PREMKUMAR NAIR · Khalapur, RaigarhP52000006375· 85.5% built· 1 complaint
- SHIREEN PLAZA7.4 yr overdueS V ENTERPRISES · MAMDAPUR, RaigarhP52000016254· 90.9% built
- ANANDI PRIDE PHASE III7.4 yr overdueANANDI ENTERPRISES · Alibag, RaigarhP52000007845· filed Mar 2018 → now Mar 2019· 66.4% built
- United Galaxy Phase 47.4 yr overdueThe United Group Of Builders And Developers · Pen (M Cl), RaigarhP52000001710· 65% built
- SAI SARANG7.4 yr overdueV B REALITIES · PANVEL, RaigarhP52000006506· 72.7% built
- RAJ HOME7.4 yr overdueHOME TOWN ENTERPRISES · Panvel, RaigarhP52000004421· 72.1% built
- NEEL SAI GANGA7.4 yr overdueVilas Madanlal Kothari · OPP SAI BABA TEMPLE, RaigarhP52000000904· 86.4% built
- NEEL RIDDHI EMERALD7.4 yr overdueNEEL RIDDHI EMERALD · Panvel, RaigarhP52000000999· 90.9% built
- SKY CANARY7.4 yr overdueAADHAR INFRA PROJECT · Uran, RaigarhP52000004704· 72.7% built
- BRAMHA VALLEY7.4 yr overdueSHREE BRAMHA ENTERPRISES · Mamdapur, RaigarhP52000008559· 21.8% built
- KANHA PLATINUM7.4 yr overdueKANHA DEVELOPERS · Gavhan, RaigarhP52000003007· 27.3% built
- TULSI SONATA7.3 yr overdueTULSI CONSTRUCTIONS · SAI NAGAR OLD PANVEL, RaigarhP52000001762· filed Jul 2018 → now Apr 2019· 64.5% built
- AKSHAT ELITE7.3 yr overdueYOGESH CONSTRUCTION · Uran, RaigarhP52000004614· 90.9% built
- QUALITY PLANET7.3 yr overdueQUALITY DEVELOPERS · Panvel, RaigarhP52000007975· filed Apr 2018 → now Apr 2019· 93% built
- SHIV AASTHA7.3 yr overdueRUPALI SUDHIR GULATI · SECTOR 21, RaigarhP52000000960· 89.5% built
- ELEGANT OLYMPIA7.3 yr overdueELEGANT HOMES · Panvel, RaigarhP51700010687· filed May 2018 → now May 2019· 90.9% built
- Omkara Prathmesh7.2 yr overdueOmkara Builders & Developers · KARANJADE, RaigarhP52000000628· 82.7% built
- NOBLE ORCHID7.2 yr overdueAMITKUMAR ZAVERCHAND SHETH · Mahad (M Cl), RaigarhP52000002417· 90.9% built
- PAWAN RESIDENCY7.2 yr overduePAWAN ENTERPRISE · Uran, RaigarhP52000011799· 90.9% built
- LA RIVERIA7.2 yr overdueLAKHANI BUILDERS PVT LTD · Panvel, RaigarhP52000001858· 80.7% built
- GULMOHAR7.2 yr overdueM/S SERENE LIFESPACES · ULWE, RaigarhP52000000719· 65.5% built
- YASH HEIGHTS7.2 yr overdueYash Developers · Navi Mumbai, RaigarhP52000007304· 73.2% built
- NEELKANTH VANDAN7.2 yr overdueROOPA ASSOCIATES · NEAR SAI MANDIR, RaigarhP52000001990· 62.9% built
- LEAF VILLA7.2 yr overdueSHREE KHODIYAR DEVELOPERS · Uran, RaigarhP52000004152· 63.6% built
- DEZINER ASTER7.1 yr overdueDEZINERS HOMES PVT. LTD. · Ulawe, RaigarhP52000006304· 90.8% built
- SAISHA RESIDENCY7.1 yr overdueSAISHA DEVELOPERS · Panvel, RaigarhP52000011420· filed Jun 2018 → now Jun 2019· 90.9% built
- TULSA NAMDEO RESIDENCY7.1 yr overdueRAM VASDEV BATHIJA · Ulawe, RaigarhP52000005472· 56.8% built· 1 complaint
- TATER FLORENCE DAISY-C WING7.1 yr overdueTATER REALTY · Karjat, RaigarhP52000010005· 88.6% built
- KRISHNA PARADISE7.1 yr overdueKRISHNA ENTERPRISES · Ulawe, RaigarhP52000012342· 42.5% built
- SAI RACHANA7.1 yr overdueSAI ASSOCIATES · Panvel, RaigarhP52000001349· 72.7% built
- SAHAKAR DWARKA I7.1 yr overdueSANKET HOMES · PANVEL, RaigarhP52000002292· filed Jun 2018 → now Jun 2019· 81.2% built
- LAKE CITY PHASE-17.1 yr overdueSADANAND LAXMANRAO PATIL · Sudhagad, RaigarhP52000001648· 70.6% built
- PLATINUM PRIDE B WING7.1 yr overdueSHREE ASHTAVINAYAK DEVELOPERS · NEAR GOKUL DAIRY, RaigarhP52000004013· 67.7% built
- Swastik7.1 yr overdueAditya Infrastructure · Karjat, RaigarhP52000009322· filed Jul 2018 → now Jun 2019· 47.3% built
- PANCHARATNA COMPLEX7.1 yr overdueHONESTY BULDER AND DEVELOPERS · Lodhivali, RaigarhP52000008880· filed Jul 2018 → now Jun 2019· 90.9% built
- ARMAAN RESIDENCY7.1 yr overdueRAIS AMIR PATEL · Panvel, RaigarhP52000005926· 50% built
- ARJUN RESIDENCY7.1 yr overdueVIJAY VASDEV BATHIJA · Taloje, RaigarhP52000012321· 61.5% built· 29 complaints
- AVAJ RESIDENCY7.1 yr overdueAVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED · Vichumbe, RaigarhP52000012402· filed Jun 2018 → now Jun 2019· 81.8% built· 7 complaints
- GOVIND SMRUTI7.1 yr overdueB.Kalyanji Realty · Khalapur, RaigarhP52000002247· 82.3% built
- LAKHANI SKYWAYS7.1 yr overdueLAKHANI BUILDERS PVT LTD · Panvel, RaigarhP52000001731· 95.5% built
- SAWAN AVENUE 27.1 yr overdueSHREE SAWAN BUILDERS & DEVELOPERS PVT LTD · Panvel, RaigarhP52000002033· 90.9% built
- Sai Siddhi Residency7.1 yr overduePrakruti Manohar Mhatre · Panvel, RaigarhP52000008529· 90.9% built
- RADHE KRISHNA7.1 yr overdueGLOBE HITECH BUILDERS · Panvel, RaigarhP52000008599· 54.5% built
- SAI GANESH7.1 yr overdueH.B. CONSTRUCTION · Uran, RaigarhP52000014929· 30% built
- Madhav Vaibhav7.0 yr overdueDolphin Developers · Khopoli, RaigarhP52000013980· 90.9% built
- ELEGANT IONA7.0 yr overdueELEGANT ENTERPRISES · Karanjade, RaigarhP52000003254· 51.8% built
- Yashoda Shrushti7.0 yr overdueJitesh Natwarlal Thakkar · Khalapur, RaigarhP52000003559· 82.3% built
- ORCHID MEADOWS7.0 yr overdueRAMESHBHAI PATEL · Ulawe, RaigarhP52000002712· 68.2% built
- PHASE 1 JAINAM GARDEN7.0 yr overdueJAINAM INFRA INDIA · Khalapur, RaigarhP52000010190· filed Sept 2018 → now Sept 2019· 79.6% built
- CHAITANYA SHREE SAMARTH KRUPA6.9 yr overdueRAJENDRA MADHUKAR JOSHI · Tal Panvel, RaigarhP52000014162· 90.9% built
- PARK VILLA6.9 yr overdueSHREE KHODIYAR DEVELOPERS · Uran, RaigarhP52000009678· 45% built
- Shubharambh Gardens6.9 yr overdueM/s Shubharambh Realty · Dhamote, RaigarhP52000009035· 80.5% built
- TROPICANA VILLAS PHASE 16.9 yr overdueTropicana Leisure Hospitality Pvt.Ltd · Mushet, RaigarhP52000010185· 89.1% built
- GAMI AVENUE6.9 yr overdueGAMI INFRA DEVELOPERS · Ulawe, RaigarhP52000013751· 90.9% built
- HAPPY HOME CHS LTD6.9 yr overdueJAY ENTERPRISES · Panvel, RaigarhP52000002992· filed Sept 2018 → now Sept 2019· 68.2% built
- RIDDHI SIDHHI APARTMENTS6.9 yr overdueM/S GOLDEE INFRASTRUCTURE · Bopele, RaigarhP52000013328· 36.4% built
- RAVECHI DEEP6.9 yr overdueSMIT KIRAN DOSHI · Ulawe, RaigarhP52000005619· 90.9% built
- Shanti Glory6.9 yr overdueAshapura Realty · Panvel, RaigarhP51700002533· 90.9% built· 1 complaint
- SARANG ARYAN6.9 yr overdueARYAN ENTRPRISES · KARANJADE, RaigarhP52000003780· 72.7% built
- PRAYAG KALASH6.9 yr overduePRAYAG DEVELOPERS · Pen (M Cl), RaigarhP52000011275· filed Dec 2018 → now Oct 2019· 90.9% built
- M/s.New Saikrupa Panvel CHS Ltd6.9 yr overdueM/s.Sai Realty · Panvel, RaigarhP52000002568· 90.9% built
- CHALAT GROUP BUILDERS AND DEVELOPERS6.8 yr overdueSUVARNA SHAJI CHALAT · Vadghar (CT), RaigarhP52000014016· 90.9% built
- CITY ELITE6.8 yr overdueM/S. STEEL CITY DEVELOPERS · ULWE NAVI MUMBAI, RaigarhP52000003317· 65% built
- JASH PRIDE6.8 yr overdueTRINETRA BUILDERS AND DEVELOPERS · KARANJADE, RaigarhP52000007656· filed Nov 2018 → now Oct 2019· 90.9% built
- Tejas Parishma6.8 yr overdueTejas Enterprises · Panvel, RaigarhP52000006095· 90.9% built
- SARAL ORCHID6.8 yr overdueSARAL ENTERPRISE · SECTOR 19, RaigarhP52000015015· 90.9% built
- TRIMURTI PROXIMA6.8 yr overdueSUBHASH FAUJDAR YADAV · Karanjade, RaigarhP52000000746· 36.4% built
- SAI KRISHNA6.7 yr overdueSRI VARI BUILDERS · Panvel, RaigarhP52000003232· 54.7% built
- SRI SAI AMRUT6.7 yr overdueSRI VARI BUILDERS · Panvel, RaigarhP52000008969· 27.5% built
- PIYUSH APARTMENT6.7 yr overduePIYUSH ENTERPRISES · BOPELE, RaigarhP52000015435· 31.8% built
- PRIME VILLA6.7 yr overdueLEERA RAMJI ARETHIYA · Panvel, RaigarhP52000004578· 63.6% built
- AANGAN VILLA6.7 yr overdueSHREE KHODIYAR DEVELOPERS · Uran, RaigarhP52000004845· 81.8% built
- Vishwa Abha6.7 yr overdueM/s. Vishwa Green Realtors Private Limited · Uran, RaigarhP52000003732· filed Dec 2018 → now Dec 2019· 90.9% built
- PARSHVA AANGAN6.6 yr overdueSONALI MEHUL DOSHI · Uran, RaigarhP51700000724· 37.6% built
- ABHISHEK FLORIDA- MARIGOLD6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004893· 90.9% built
- ARIHANT ANSHULA6.6 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Navi Mumbai, RaigarhP52000009246· 85.5% built· 1 complaint
- ABHISHEK FLORIDA- LOTUS6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005376· 90.9% built
- ABHISHEK FLORIDA- ORCHID6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000004263· 90.9% built
- ABHISHEK FLORIDA- BLOSSOM6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000008362· 90.9% built
- ABHISHEK FLORIDA- SUNFLOWER, ROSE, JASMINE6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005897· 90.9% built· 1 complaint
- ABHISHEK FLORIDA- DAFFODILS6.6 yr overdueM/s. Seema Promoters And Builders Private Limited · Neral, RaigarhP52000005514· 90.9% built
- SHIVALAY APARTMENT6.6 yr overdueShivalay Developers · Ulawe, RaigarhP52000009972· 90.9% built
- SAILEELA6.6 yr overdueDENNIS JAMES FERNANDES · KHALAPUR, RaigarhP52000010923· filed Dec 2018 → now Dec 2019· 86.4% built
- PARVATI ARCADE6.6 yr overdueCHANDRAKAUMUDI CONSTRUCTION · Mahad, RaigarhP52000001957· 90.9% built
- AMBIKA HERITAGE6.6 yr overdueRADHA MEERA BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000003237· filed Dec 2018 → now Dec 2019· 90.9% built· 1 complaint
- SHUBHAM APARTMENT6.6 yr overdueRAMESH GULAB TUPE · VILLAGE PUSHPAK NODE , TALUKA PANVEL, RaigarhP52000015885· 90.9% built
- Aayushi Apartment6.6 yr overduePRIYANSHI ENTERPRISES · Karanjade, RaigarhP52000005046· 27.3% built
- JIN YASH6.6 yr overdueContendre Infratech Pvt. Ltd. · SHILPHATA, RaigarhP52000017145· 90.9% built
- RIVERSIDE GREENS6.6 yr overdueGROW PLUS INFRA · Umroli, RaigarhP52000005275· filed Dec 2018 → now Dec 2019· 87.6% built· 2 complaints
- Alpine Heritage6.6 yr overdueALPINE SKYSCRAPERS LLP · NA, RaigarhP52000015494· 81.8% built
- PRATHAM RESIDENCY6.6 yr overdueADARSH ENTERPRISES · Uran, RaigarhP52000005240· 90.9% built
- SAI DEEP6.6 yr overdueSAMBHAV PROJECTS · PANVEL, RaigarhP52000004098· 81.8% built
- Rachana One Up6.6 yr overdueRachana Value Homes Pvt Ltd · Bopele, RaigarhP52000002087· 81.8% built
- ARAMUS COMPLEX6.6 yr overdueGURUKRUPA GROUP BUILDERS AND DEVELOPERS · Panvel, RaigarhP52000007602· filed Dec 2018 → now Dec 2019· 74.7% built
- SHIV RESIDENCY6.6 yr overdueSHIV ENTERPRISE · Panvel, RaigarhP52000004793· 36.4% built
- AKSHAT PRIME6.6 yr overdueYOGESH CONSTRUCTION · Uran, RaigarhP52000002802· 90.9% built
- USHAPRABHA CHS6.6 yr overdueSHASHIKANT GAJANAN POTE · Panvel, RaigarhP52000007082· 90.9% built
- MILLENIUM EMPIRE6.6 yr overdueBHARAT CONSTRUCTION · Panvel, RaigarhP52000001042· 75.2% built
- SHREE SADGURU COMPLEX PHASE I6.6 yr overdueEARTH HOME · Khalapur, RaigarhP52000011306· 90.9% built
- SHIVAM APARTMENT6.6 yr overdueGOPIKRISHNA PRABHAKARAN NAIR · Neral, RaigarhP52000008618· 73.2% built
- MARATHON NEXZONE ZODIAC -26.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000661· 72.7% built· 2 complaints
- POTE AALAYA6.6 yr overduePRAKASH GAJANAN POTE · Near Mari aai Temple, RaigarhP52000001069· 90.9% built
- NEELKANTH AURA6.6 yr overdueNEELKANTH LIFESPACE LLP · NAVI MUMBAI, RaigarhP52000007335· 88% built
- SAI SHRADDHA6.6 yr overdueBALAJI ENTERPRISES · BOPELE, RaigarhP52000015196· 40.9% built
- Eden Garden II6.6 yr overdueM C Babu · Uran, RaigarhP52000008714· 82.5% built
- Aayushi Heights6.6 yr overduePRIYANSHI ENTERPRISES · Panvel, RaigarhP52000005007· 18.2% built
- AKSHAR EDEANIA6.6 yr overdueVAGAD CONSTRUCTIONS · Uran, RaigarhP52000006744· filed Dec 2018 → now Dec 2019· 85.9% built· 1 complaint
- SHIVAM PALACE6.6 yr overdueSHIVAM CONSTRUCTION · MAMDAPUR, RaigarhP52000015309· 81.4% built
- SHREE POOJA6.6 yr overdueMANGALAM BUILDCON · NERAL, RaigarhP52000001841· 81.8% built
- Tejas Emerald6.6 yr overdueTejas Enterprises · Panvel, RaigarhP52000009591· 90.9% built
- SUNRISE HOMES6.6 yr overdueKHALIF SIRAJ SHAIKH · Damat, RaigarhP52000010277· 61.8% built
- BALAJI DARPAN6.6 yr overdueBALAJI INFRA · Panvel, RaigarhP52000005816· 49.4% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.