High risk
  • Possession date passed. The proposed possession date (Aug 2019) has passed with construction at 68.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2019 per the RERA filing.
Satellite view of this address

Where it is · 10, Ulawe

Promoter

Builder profile

Builder
RAMESHBHAI PATEL

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000002712
Status
Ongoing
Stage
Certificate Signed
Possession
August 2019
Construction
68.2% complete
Units sold
0 of 0

Similar projects in Ulawe

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ulawe compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.