Under construction
KAJAL PRIDE
MahaRERA P52000014535High risk
PLOT NO 1 SURVEY NO 29 HISSA NO 2A AND PLOT NO 7 SURVEY NO 29 HISSA NO 2B, KARJAT, 410201
Post your property hereOwn or renting out a unit in KAJAL PRIDE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KARJAT come to you.
Dec 2019
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2019 per the RERA filing.
Satellite view of this address
Where it is · PLOT NO 1 SURVEY NO 29 HISSA NO 2A AND PLOT NO 7 SURVEY NO 29 HISSA NO 2B, KARJAT
Promoter
Builder profile
DEEPAK BHAICHAND SHAH
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000014535
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in KARJAT
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
BALI IXORA PHASE - 1
KARJATPoss. June 2028
TRULIFE
KARJATPoss. July 2027
VICTORIA HILLS PHASE - 2
KARJATPoss. October 2026
MUDRA AVENUE
KARJATPoss. April 2029
GAJVAKRA PRIME
KARJAT172.7% builtPoss. December 2025
LAXMI ORCHID
KARJAT100% builtPoss. June 2021
SURYA GALAXY PHASE I
KARJAT100% builtPoss. July 2022
ETERNIA SPACE PHASE II
KARJAT100% builtPoss. April 20272 complaints
Keep exploring
Where this project sits, who built it, and how KARJAT compares.
In KARJAT
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.