Under construction

Rosa Oasis Phase 3

MahaRERA P51700006155High risk

by Uma Enterprises

s.no. 124/2/3, 125/2, 125/3/1, 125/3/2, 125/4 and 125/5, Thane, 400615

Official record
Dec 2017
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 90.9%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2017 per the RERA filing.
Satellite view of this address

Where it is · s.no. 124/2/3, 125/2, 125/3/1, 125/3/2, 125/4 and 125/5, Thane

Promoter

Builder profile

Builder
Uma Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700006155
Status
Ongoing
Stage
Certificate Signed
Possession
December 2017
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.