Under construction

POONAM ESTATE CL 2 BLG NO 1 2 3

MahaRERA P51700009072High risk

by Ravi Developments

OLD SURVEY NO 226 227 228 229 230 PENKARPADA 150 151 MIRA, MIRA ROAD EAST, 401107

Official record
Mar 2018
Possession
95.5%
Built
0
Complaints
0
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 95.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.
Satellite view of this address

Where it is · OLD SURVEY NO 226 227 228 229 230 PENKARPADA 150 151 MIRA, MIRA ROAD EAST

Area guide

What it's like to buy in MIRA ROAD EAST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Dahisar / Mira RoadValue

The city's northern value frontier, densifying fast.

Growth drivers:
Metro 9 extension, spillover from Borivali pricing.
Who buys here:
First-time buyers stretching for a 1–2 BHK.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Ravi Developments

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700009072
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
95.5% complete
Units sold
0 of 0

Similar projects in MIRA ROAD EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MIRA ROAD EAST compares.

Data sourced from the official MahaRERA portal; complaints last synced 20 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.