Gaurav Excellency
863,4,868AtoC,871B, Harkesh Uday Nagar, 400107
- Mortgaged to a lender (₹45 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹45 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Mar 2027 per the RERA filing.
- 51 RERA complaints. 51 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Where it is · 863,4,868AtoC,871B, Harkesh Uday Nagar
Area guide
What it's like to buy in Harkesh Uday Nagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The city's northern value frontier, densifying fast.
- Growth drivers:
- Metro 9 extension, spillover from Borivali pricing.
- Who buys here:
- First-time buyers stretching for a 1–2 BHK.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700006232
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2023
- Construction
- 70.1% complete
- Units sold
- 375 of 489
Keep exploring
Where this project sits, who built it, and how Harkesh Uday Nagar compares.
In Harkesh Uday Nagar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.