All RERA projects
🏗️
Under construction

DAISY GARDENS SURVEY NO 12 PHASE II

MahaRERA P51700009095Caution

by ANKITA BUILDERS

SURVEY NO 12/12,15/7 AND 12/3 CTS NO 33/10, Ambarnath, 421505

Official record
Jul 2018
Possession
89.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2018) has passed with construction at 89.1%.
Satellite view of this address

Where it is · SURVEY NO 12/12,15/7 AND 12/3 CTS NO 33/10, Ambarnath

Area guide

What it's like to buy in Ambarnath

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ambernath / BadlapurValue

The value frontier beyond Kalyan — low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
ANKITA BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700009095
Status
Ongoing
Stage
Certificate Signed
Possession
July 2018
Construction
89.1% complete
Units sold
0 of 0

Similar projects in Ambarnath

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Ambarnath compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.