High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 76.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.
Satellite view of this address

Where it is · Sr.No.155 H.No 9/A, Thane

Promoter

Builder profile

Builder
PRAVIN SAKHARAM PATIL

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700010086
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
76.4% complete
Units sold
0 of 0

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.