Under construction

Centilia

MahaRERA P51700010837High risk

by Acme Housing India Private Limited

CTS NO GAT NO61/1/1, GAT NO61/1/2,3,4, GAT NO 61/2/1,2,3, Thane (M Corp.), 400607

Official record
Dec 2017
Possession
54.5%
Built
1
Complaints
0
Units
High risk
  • Litigation pending (6). MahaRERA's litigation disclosure lists 6 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 54.5%.
Satellite view of this address

Where it is · CTS NO GAT NO61/1/1, GAT NO61/1/2,3,4, GAT NO 61/2/1,2,3, Thane (M Corp.)

Area guide

What it's like to buy in Thane (M Corp.)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Thane (Ghodbunder belt)Mid-income

A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Acme Housing India Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51700010837
Status
Ongoing
Stage
Certificate Signed
Possession
December 2017
Construction
54.5% complete
Units sold
0 of 0

Similar projects in Thane (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.