Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 52.7%.
Satellite view of this address

Where it is · S. NO.92, Tathwade

Promoter

Builder profile

Builder
LABH PROMOTERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100013679
Status
New
Stage
Certificate Signed
Possession
March 2019
Construction
52.7% complete
Units sold
0 of 0