High risk
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 47.7%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due May 2023 per the RERA filing.
Satellite view of this address

Where it is · 145/1B, JEEVAN NAGAR

Promoter

Builder profile

Builder
M/S KRISALA ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100021234
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
47.7% complete
Units sold
0 of 0