Under construction
41 EVOKE
MahaRERA P52100028595High risk
74/1B, 74/1A/1B, 74/1A/1B/1, 74/1A/1B/2, 74/1A/1B/3, 74/1A/1B/4, RAVET, 412101
Post your property hereOwn or renting out a unit in 41 EVOKE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in RAVET come to you.
Jul 2024
Possession
43%
Built
1
Complaints
0
Units
High risk
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 43%.
- Promised amenities not started. Swimming Pool, Clubhouse, Landscaped Garden are at 0% build with possession due Jul 2024 per the RERA filing.
Area guide
What it's like to buy in RAVET
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
KRISALA ASSOCIATES
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100028595
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2024
- Construction
- 43% complete
- Units sold
- 0 of 0
Similar projects in RAVET
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
THE UNICORN BUILDING C WING C1 & C2
RAVETPoss. December 2027
VIVANTA NEST
RAVETPoss. August 2027
Raajlaxmi Greens a and b
RAVET100% builtPoss. October 2019
SILVER PALM GROVE PHASE 2
RAVET100% builtPoss. December 20192 complaints
SILVER GRACIA
RAVET100% builtPoss. December 2023
64 MERIDIEN PHASE I
RAVET100% builtPoss. October 2024
RAAJLAXMI GREENS D WING
RAVET100% builtPoss. June 2022
SILVERLAND RESIDENCY PHASE II
RAVET100% builtPoss. June 2022
Keep exploring
Where this project sits, who built it, and how RAVET compares.
In RAVET
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.