High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.
Satellite view of this address

Where it is · 26/1/6, 26/3/1, 26/3/2, Punawala

Area guide

What it's like to buy in Punawala

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Tirupati Skyscrapers LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
VK a architecture

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100051790
Status
New
Stage
Certificate Signed
Possession
September 2027
Construction
69.6% complete
Units sold
447 of 544