71 Midtown
by Paradigm Dotom Buildheights LLP
343 part, Kurla, 400071
- Mortgaged to a lender (₹100 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹100 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Dec 2026 but construction is only at 19.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · 343 part, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800028761
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2025
- Construction
- 19.5% complete
- Units sold
- 396 of 536
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.