9 DIVINE
by SACH GORWANI REAL PROJECTS PRIVATE LIMITED
F/481, Andheri, 400050
- Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Mar 2027 per the RERA filing.
- Behind schedule. Possession is due Mar 2027 but construction is only at 43.6%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Where it is · F/481, Andheri
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800045616
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2025
- Construction
- 43.6% complete
- Units sold
- 7 of 19
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.