Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Satellite view of this address

Where it is · S No. 93/1B, Autade-Handewadi, Taluka - Haveli

Area guide

What it's like to buy in Autade-Handewadi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
RHYTHM LAND DEVELOPERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DEEPAK HONKAN

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100080367
Status
New
Stage
Certificate Signed
Possession
March 2035
Construction
4.5% complete
Units sold
2 of 100

Keep exploring

Where this project sits, who built it, and how Autade-Handewadi, Taluka - Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.