A. H. Heights
50,50/1 to 12, Jogeshwari West, 400102
- Possession delayed ~6 yrs. Originally promised Aug 2022, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2028 per the RERA filing.
Where it is · 50,50/1 to 12, Jogeshwari West
Area guide
What it's like to buy in Jogeshwari West
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Entertainment-industry heartland — dense, lively, well connected.
- Growth drivers:
- Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
- Who buys here:
- Media professionals, first upgraders, rental investors.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800012784
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2028originally August 2022
- Construction
- 88.6% complete
- Units sold
- 38 of 109
Similar projects in Jogeshwari West
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Jogeshwari West compares.
In Jogeshwari West
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.