Under construction

AABIEL HEIGHTS

MahaRERA P51700006603High risk

by DAICHI INFRA LLP

Survey no 570/2 Village Bhayander, Meera Hospital, 401101

Official record
Jul 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Aug 2022, now proposed Jul 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 90.9%.
Satellite view of this address

Where it is · Survey no 570/2 Village Bhayander, Meera Hospital

Promoter

Builder profile

Builder
DAICHI INFRA LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700006603
Status
Ongoing
Stage
Certificate Signed
Possession
July 2024originally August 2022
Construction
90.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Meera Hospital compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.