🏗️
Under construction
Aangan Phase II
MahaRERA P52100019915High risk
3/3/2 p, Mawal, 410507
Post your property hereOwn or renting out a unit in Aangan Phase II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mawal come to you.
Dec 2022
Possession
2.3%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 2.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address
Where it is · 3/3/2 p, Mawal
Area guide
What it's like to buy in Mawal
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Galaxy Associates
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100019915
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2022
- Construction
- 2.3% complete
- Units sold
- 0 of 0
Similar projects in Mawal
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Vaarivana Phase D - 2A
MawalPoss. October 2026
Vaarivana Phase D - 2B
MawalPoss. August 20271 complaint
Riverland Ph 2
MawalPoss. December 2028
Riverland Ph 1
MawalPoss. December 2028
Urbanbrick Castle Phase 2
MawalPoss. December 2028
GREENDALE ENA
MawalPoss. December 2026
RIVERLAND PH-4
MawalPoss. December 2028
RIVERLAND PH-5
MawalPoss. December 2028
Keep exploring
Where this project sits, who built it, and how Mawal compares.
In Mawal
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.