Aapla Ghar Ambegaon Annex Phase I

MahaRERA P52100008761High risk

by Maple Buildcon

224 A and 224 B Part, Bhor, 412206

Official record
Dec 2029
Possession
37.1%
Built
18
Complaints
134
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~6 yrs. Originally promised Dec 2023, now proposed Dec 2029 per the RERA filing.
  • 18 RERA complaints. 18 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 224 A and 224 B Part, Bhor

Area guide

What it's like to buy in Bhor

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Maple Buildcon

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Insignis Architecture

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100008761
Status
Ongoing
Stage
Certificate Signed
Possession
December 2029originally December 2023
Construction
37.1% complete
Units sold
110 of 134

Similar projects in Bhor

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Bhor compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.