All RERA projects
🏗️
Under construction

Aapla Ghar Moshi Annex Phase I

MahaRERA P52100002998High risk

by Maple Shelters Pvt. Ltd.

184 and others, Khed, 410501

Official record
Dec 2027
Possession
65%
Built
6
Complaints
296
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 184 and others, Khed

Area guide

What it's like to buy in Khed

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Maple Shelters Pvt. Ltd.

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Jay aeram Architectural and interior consultant

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100002998
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
65% complete
Units sold
280 of 296

Similar projects in Khed

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Khed compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.