High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 49.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO 44 SECTOR 56, DRONAGIRI URAN

Area guide

What it's like to buy in DRONAGIRI URAN

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
LAMBODAR INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
VASTUYOG ARCHITECTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000052524
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
49.5% complete
Units sold
14 of 29

Keep exploring

Where this project sits, who built it, and how DRONAGIRI URAN compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.