High risk
  • Behind schedule. Possession is due Jul 2027 but construction is only at 33.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · 45/2, WANJARWADI

Promoter

Builder profile

Builder
SANJAY MAHADEO CHOUDHAR

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
NILAM YADAV

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100077597
Status
New
Stage
Certificate Signed
Possession
July 2027originally March 2027
Construction
33.2% complete
Units sold
0 of 68