Under construction

ACE AASTHA BUILDING C

MahaRERA P52100024476High risk

by SAKSHI DEVELOPERS

SURVEY NO. 166/3, 166/4, 167/1, 167/2, 167/3A, OPP. TANISHQ ORCHID SOCIETY, 412105

Official record
Sept 2025
Possession
87.7%
Built
11
Complaints
110
Units
High risk
  • 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Sept 2025) has passed with construction at 87.7%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Sept 2025 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. 166/3, 166/4, 167/1, 167/2, 167/3A, OPP. TANISHQ ORCHID SOCIETY

Area guide

What it's like to buy in OPP. TANISHQ ORCHID SOCIETY

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SAKSHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
VKa Architecture

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100024476
Status
New
Stage
Certificate Signed
Possession
September 2025originally October 2024
Construction
87.7% complete
Units sold
93 of 110