Under construction
Ace Aria
MahaRERA P51600051453High risk
Plot No. 1+2 of S. No. / G. No. 501/2 To 15/1/26, F.P. No. 25, TPS-ll of Nashik Shiwar, Nashik 422011, Bhabha Nagar, 422011
Post your property hereOwn or renting out a unit in Ace Aria? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Bhabha Nagar come to you.
Aug 2027
Possession
60.9%
Built
0
Complaints
14
Units
High risk
- Possession delayed ~1 yr. Originally promised Apr 2026, now proposed Aug 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2027 per the RERA filing.
Promoter
Builder profile
ACE Developers
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51600051453
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2027originally April 2026
- Construction
- 60.9% complete
- Units sold
- 7 of 14
Similar projects in Bhabha Nagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Bhabha Nagar compares.
The developer
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.