Under construction

Adhiraj Samyama Tower 1D

MahaRERA P52000014856High risk

by Adhiraj Constructions Private Limited

Survey no 70 hissa no 1, Survey no 70 hissa no 2, -, 410208

Official record
Mar 2027
Possession
32.1%
Built
5
Complaints
218
Units
High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • Mortgaged to a lender (₹525 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹525 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~4 yrs. Originally promised Jul 2023, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 32.1%.
Satellite view of this address

Where it is · Survey no 70 hissa no 1, Survey no 70 hissa no 2, -

Area guide

What it's like to buy in this area

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Adhiraj Constructions Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Nitin Honawar

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000014856
Status
New
Stage
Certificate Signed
Possession
March 2027originally July 2023
Construction
32.1% complete
Units sold
194 of 218

Similar projects in Raigarh

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.