High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 72.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 27/4/2 AND 27/4/3, Ahead Balaji Temple

Area guide

What it's like to buy in Ahead Balaji Temple

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
M/S J.N.BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100025763
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
72.5% complete
Units sold
0 of 0