High risk
  • Possession delayed ~1 yr. Originally promised Dec 2024, now proposed Jun 2026 per the RERA filing.
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 50.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address

Where it is · 36/3, Mohammadwadi, Haveli

Promoter

Builder profile

Builder
Briskband Associates

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100019898
Status
New
Stage
Certificate Signed
Possession
June 2026originally December 2024
Construction
50.9% complete
Units sold
0 of 0

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.