High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 43.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · CTS NO.661/1 PART, 661/2, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

MulundUpper-mid

Leafy eastern-suburb favourite with big redevelopment supply.

Growth drivers:
Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
Who buys here:
Eastern-suburb families upgrading within the area.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
ALAG PROPERTY CONSTRUCTIONS PVT. LTD.

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800020773
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2024
Construction
43.6% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.