High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Jul 2027 per the RERA filing.
  • 21 RERA complaints. 21 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Jul 2027 but construction is only at 3.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · 20/1 AND 21/1, Vihour

Promoter

Builder profile

Builder
COREDELIA REALTY PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000011624
Status
Ongoing
Stage
Certificate Signed
Possession
July 2027originally June 2021
Construction
3.8% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Vihour compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.