High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Jul 2027 per the RERA filing.
Satellite view of this address

Where it is · S NO 79 PLOT NO 1, MAMDAPUR

Promoter

Builder profile

Builder
UNITY CONSTRUCTION

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
VASTU RACHANA CONSULTANCY

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000030922
Status
New
Stage
Certificate Signed
Possession
July 2027originally December 2023
Construction
67.7% complete
Units sold
26 of 64

Similar projects in MAMDAPUR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MAMDAPUR compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.