Allure
Plot 85,93,94,95,96 Gat No. 849 to 854, Wagholi, 412207
- Possession delayed ~3 yrs. Originally promised Mar 2019, now proposed Jun 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 86.4%.
- Promised amenities not started. Swimming Pool is at 0% build with possession due Jun 2022 per the RERA filing.
Where it is · Plot 85,93,94,95,96 Gat No. 849 to 854, Wagholi
Area guide
What it's like to buy in Wagholi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100002402
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally March 2019
- Construction
- 86.4% complete
- Units sold
- 0 of 0
Similar projects in Wagholi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Wagholi compares.
In Wagholi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.