Under construction

AMAR INFINITY

MahaRERA P52100000614Caution

by AMAR HARISHCHANDRA MANJREKAR

Survey No 198/2, 200, 201/1 to 8, 10 to 14, 205/3to8, 206/4a,4b,207/1 to 6, Baner, 411045

Official record
Dec 2026
Possession
0.6%
Built
0
Complaints
68
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 0.6%.
Satellite view of this address

Where it is · Survey No 198/2, 200, 201/1 to 8, 10 to 14, 205/3to8, 206/4a,4b,207/1 to 6, Baner

Promoter

Builder profile

Builder
AMAR HARISHCHANDRA MANJREKAR

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100000614
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026
Construction
0.6% complete
Units sold
0 of 68

Similar projects in Baner

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Baner compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.