Under construction

Ambit Vista

MahaRERA P51800052265High risk

by Ambit Vista

CTS No. 2046, 2048 of village vile parle East & CTS No. 5 of vill. Bandra I ward and F.P. No. 138 & 139 Santacruz TPS-V, Tal. Andheri with CTS No. 2049 of vill. Vile Parle East, Tal. Andheri F.P. No. 137 Santacruz TPS-V, Santacruz East, Mumbai - 400 055, Andheri, 400055

Official record
Dec 2026
Possession
52.8%
Built
1
Complaints
103
Units
High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · CTS No. 2046, 2048 of village vile parle East & CTS No. 5 of vill. Bandra I ward and F.P. No. 138 & 139 Santacruz TPS-V, Tal. Andheri with CTS No. 2049 of vill. Vile Parle East, Tal. Andheri F.P. No. 137 Santacruz TPS-V, Santacruz East, Mumbai - 400 055, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Santacruz / KharUltra-luxury

Bandra's quieter northern neighbour — low-rise lanes going boutique.

Growth drivers:
Society redevelopment, airport and BKC equidistance.
Who buys here:
Professionals wanting Bandra adjacency with less noise.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Ambit Vista

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Skyline Inframart Consultants LLP

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800052265
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
52.8% complete
Units sold
78 of 103

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.