High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Gymnasium, Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Satellite view of this address

Where it is · Plot No 28, Sector 17

Area guide

What it's like to buy in Sector 17

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Pushpam Infrastructure Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000013131
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2019
Construction
60.5% complete
Units sold
19 of 54

Similar projects in Sector 17

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Sector 17 compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.