Under construction

Anand Kirti Tower

MahaRERA P99000003076High risk

by S R and Shah Developers

S no 31 135 H no 2, S no 31 135 H no 5A, S no 31 135 H no 5 B, S no 31 135 H no 8, Dongare, 401303

Official record
Dec 2026
Possession
58.4%
Built
38
Complaints
114
Units
High risk
  • 5 appeals at MahaREAT. 5 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • 38 RERA complaints. 38 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · S no 31 135 H no 2, S no 31 135 H no 5A, S no 31 135 H no 5 B, S no 31 135 H no 8, Dongare

Area guide

What it's like to buy in Dongare

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
S R and Shah Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000003076
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
58.4% complete
Units sold
54 of 114

Similar projects in Dongare

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Dongare compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.