- Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 90%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2025 per the RERA filing.
Where it is · PLOT NO 114,115,132,133/ CTS NO 79 SHEET NO 16 (187/B) AND 600(17), RAJENDRA NAGAR,HINGNA ROAD
Area guide
What it's like to buy in RAJENDRA NAGAR
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P50500049002
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2025originally April 2025
- Construction
- 90% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how RAJENDRA NAGAR,HINGNA ROAD compares.
In RAJENDRA NAGAR,HINGNA ROAD
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.