High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2019, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 95.5%.
Satellite view of this address

Where it is · CTS No. 1188, Sr. No. 61/1/1, Pune City

Promoter

Builder profile

Builder
DAJIKAKA GADGIL DEVLOPERS .PVT.LTD .

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100001340
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023originally December 2019
Construction
95.5% complete
Units sold
0 of 0

Similar projects in Pune City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pune City compares.

Data sourced from the official MahaRERA portal; complaints last synced 23 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.