ANANTSRISHTI PHASE I
GUT NO 387 AND 404, JAMBHUL, 412106
- Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
- 3 appeals at MahaREAT. 3 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- 11 RERA complaints. 11 complaint records are disclosed against this project on MahaRERA.
Where it is · GUT NO 387 AND 404, JAMBHUL
Area guide
What it's like to buy in JAMBHUL
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100006401
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 100% complete
- Units sold
- 122 of 123
Similar projects in JAMBHUL
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how JAMBHUL compares.
In JAMBHUL
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.