ANMOLPRITI
by Muktistar Buildcon Private Limited
1/C/1/231 / PLOT NO 156, Borivali, 400067
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~6 yrs. Originally promised Dec 2018, now proposed Jun 2025 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 89.7%.
Where it is · 1/C/1/231 / PLOT NO 156, Borivali
Area guide
What it's like to buy in Borivali
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Self-sufficient Gujarati-dominated family belt beside the National Park.
- Growth drivers:
- Metro 2A/7, station upgrades, big-brand township launches.
- Who buys here:
- Families seeking space and community at sane prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800006598
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2025originally December 2018
- Construction
- 89.7% complete
- Units sold
- 0 of 0
Similar projects in Borivali
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Borivali compares.
In Borivali
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.