High risk
  • 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Jan 2027 per the RERA filing.
  • 17 RERA complaints. 17 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jan 2027 per the RERA filing.
Satellite view of this address

Where it is · S NO. 257, HADAPSAR

Promoter

Builder profile

Builder
ACE CONSTRUCTIONS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Element 5

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100020764
Status
New
Stage
Certificate Signed
Possession
January 2027originally December 2023
Construction
81.8% complete
Units sold
175 of 188

Similar projects in HADAPSAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how HADAPSAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.