APOLLO 2
by M/S SHADOW BUILDERS AND DEVELOPERS PVT LTD
59 c, Panvel, 410210
- 4 appeals at MahaREAT. 4 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Feb 2022 per the RERA filing.
- 31 RERA complaints. 31 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 46.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2022 per the RERA filing.
Where it is · 59 c, Panvel
Area guide
What it's like to buy in Panvel
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The airport-bet frontier — golf course, hills and heavy new supply.
- Growth drivers:
- Navi Mumbai International Airport, MTHL access, NAINA planning zone.
- Who buys here:
- First-time buyers and investors betting on the airport economy.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000007231
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- February 2022originally December 2018
- Construction
- 46.2% complete
- Units sold
- 0 of 0
Similar projects in Panvel
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Panvel compares.
In Panvel
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.