High risk
  • Possession delayed ~5 yrs. Originally promised Jul 2022, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address

Where it is · 138/2B/2 and others, Haveli

Area guide

What it's like to buy in Haveli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Thane (Ghodbunder belt)Mid-income

A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.

Growth drivers:
Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
Who buys here:
Families upgrading to space and amenities without island-city prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Sri Sidhievinayak associetes

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
ANKUR ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100011604
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally July 2022
Construction
80% complete
Units sold
68 of 269

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.