High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 89.6%.

Area guide

What it's like to buy in Andheri West

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
PRATHAM VIGHNAHARTA INFRACON LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Prathamesh Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800049426
Status
New
Stage
Certificate Signed
Possession
October 2025originally June 2025
Construction
89.6% complete
Units sold
54 of 104

Similar projects in Andheri West

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri West compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.