High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 10%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Promoter

Builder profile

Builder
KAPIL VILASRAO BARGE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100021905
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
10% complete
Units sold
0 of 0