High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 10%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Area guide

What it's like to buy in SHARDANAGAR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KAPIL VILASRAO BARGE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100021905
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
10% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how SHARDANAGAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.