Under construction

ASHISH BUILDING OF EMTICIBOM EMPLOYEES CHS LTD

MahaRERA P51800027525High risk

by KARWA AND KEWAL KIRAN REALTORS

PLOT NO 13, CTS NO 836, 8362, 8363, 8364, 8365, CHINCHOLI PHATAK, MALAD WEST, 400064

Official record
Sept 2024
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2024 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO 13, CTS NO 836, 8362, 8363, 8364, 8365, CHINCHOLI PHATAK, MALAD WEST

Area guide

What it's like to buy in CHINCHOLI PHATAK

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
KARWA AND KEWAL KIRAN REALTORS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800027525
Status
New
Stage
Certificate Signed
Possession
September 2024
Construction
0% complete
Units sold
0 of 0