Under construction

Ashwini Apartment

MahaRERA P52000052886High risk

by Kuldeepsingh Amarsingh Bhalothia

Plot No -174+175, Unit No.-5, Sector No.-21, Kharghar, Navi Mumbai, 410210

Official record
Dec 2026
Possession
78.2%
Built
0
Complaints
10
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · Plot No -174+175, Unit No.-5, Sector No.-21, Kharghar, Navi Mumbai

Area guide

What it's like to buy in Kharghar

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kharghar / PanvelValue

The airport-bet frontier — golf course, hills and heavy new supply.

Growth drivers:
Navi Mumbai International Airport, MTHL access, NAINA planning zone.
Who buys here:
First-time buyers and investors betting on the airport economy.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Kuldeepsingh Amarsingh Bhalothia

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Vaibhav Patil & Architects

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52000052886
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
78.2% complete
Units sold
3 of 10

Similar projects in Kharghar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kharghar, Navi Mumbai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.